Thursday, December 18, 2008

Flooring abatement

Facilities is planning to do some flooring abatement. Here is the current schedule:

· Winter break 2008 – hallways, stairwells and room 009. Nothing that should effect IT.

· Summer 2009 – Possible floor abatement in rooms 121, 224, 225 and 322. Facilities wants to push this out to Winter 2009 if possible and then leave the rooms unoccupied.
o All equipment and furniture will need to be removed from the rooms, including SIWS units
o Room 322 is currently being used as a computer lab for the Rockville Physics Department

· FIP will continue to monitor the tentative schedule for changes.

---------------------

Ray and Steve to do walkthru in the new year to identify IT closets and other issues affecting the renovation project..