Thursday, March 18, 2010

Progress update

Biweekly programming meetings to review and discuss IT related designs and changes.
Reviewed room design of furniture with client. The client will communicate among themselves to determine the type of computer lab furniture they will choose. This will also assist in determining the type workstation for the room.

Meet with client to determine their IT requirements for workstations and furniture. Still undetermined at this point.

The NE team members are working on the telecomm room rack layout and dimension required for infrastructure equipment.

Future DD review meeting is scheduled for March 18th to review IT standards with architects, facilities, engineers and IT team members.

Monday, March 8, 2010

Progress Update

The project is still in the programming phase. Biweekly meetings are held with the architects, facilities, and engineers.

I am working with the college NE’s on telecomm rack design.

Planned future meetings are scheduled in April with the IT college team.