Estimated Project Timeline

2010 - 2011 – Participate in development, participates in planning, budget development, & construction planning (meetings and requirements development) – ensure appropriate IT groups are consulted. SCIENCE EAST ONLY

2010 - Spring 2011 – Develop IT project requirements and plan IT implementation project (finalize requirements, finalize SOW, and build team)

2011 Spring - Two or more CD reviews (65% & 100%)

2011 BID for Construction Contractor

TBD - First State Submittal

TBD - Second State Submittal

2011 - 2012 - Participate in construction activities (monitoring, inspections, and corrections). Demolition of the building to begin Fall 2011

2011 - 2012 – IT pre-building access implementation activities (procurements, deliveries, configuration burn-in,)

2012 / 2013 – IT in-building implementation activities (installation, integration and testing of network, telephone, audio visual, Wi-Fi, and desktop equipment)

Mar. 2013 – Client move in

Spring 2013 Opening