Tuesday, September 13, 2011

Rockville Science East Renovation

All occupants of the Science East building have been moved to new locations either in the new Science Center or into Science West. Clean out of building has begun under the leadership of Central Facilities. The Science East building was offically closed to the general public on August 17, 2011. IT is in the process of removing that building infrastructure that will be re-used in other College locations. The tentative schedule for the building is;


  • Remediation of Asbestos September - November 2011

  • General Renovation December 2011 - December 2012

  • Re-Opening Spring/Summer 2013