IT has submitted proposed WiFi access point location drawings to Central Facilities and the architect for a future contract bulletin to the Science East contract.
A recommendation has been returned to IT and Central Facilities from the academic area recommending only a single "Bright Link" style project be installed in Science East classrooms. The remainder to the projectors will continue to be the College standard mounted in the center of the room.
This item has also been forwarded Central Facilities for inclusion in a future contract bulletin.
The abatement contractor has discovered additional asbestos to be abated surrounding 75 windows that need to be removed. This will add delay to them completing their work.
Whiting Turner anticipates initial installation of construction zone fencing limiting access around the Science East building starting late January 2012.